How long a kitchen really takes.

How Long Does a Kitchen Remodel Take? Planning & Construction Timeline

The phases of a kitchen remodel, from the first call to the final walkthrough, and what speeds it up or slows it down.

dRemodeling crew working on walls and ceiling during a kitchen remodel in the Philadelphia area

About 5–6 months

Typical overall timeline

9–12 weeks

Construction, same layout

12+ weeks

Construction, new layout

Updated November 8, 2026 · 4 min read · Reviewed by Dan Dragomir, founder of dRemodeling

Kitchen remodel timeline at a glance

PhaseWhat happensTypical length
1. Getting startedDiscovery call, home assessment and showroom consultation; your Design Retainer and Labor Proposal followAbout 2–3 weeks
2. DesignLayouts, drawings, 3D renderings and final material selections with your designerAbout 4–6 weeks
3. Ordering & deliveryMaterials ordered and delivered; permits applied for; crew scheduledAbout 4–6 weeks
4. Construction in your homeDemolition through cabinets, counters, finishes and punch listAbout 9–12 weeks (12+ with a new layout)
5. Final walkthroughWe review the work with you and complete any last touch-upsA few days

Typical dRemodeling kitchen. Overall, about 5–6 months from the first call to a finished kitchen; a new layout or structural work takes longer. Timelines are based on typical construction durations and are not guaranteed. A more detailed schedule is provided once the project scope is confirmed.

Demolition starts once your materials have arrived, so your kitchen isn’t torn apart while everyone waits for a delivery.

Planning often takes as long as building. That’s a good thing: every decision made before demolition is one that can’t delay the crew later.

Getting started and design

After the discovery call we visit your home to measure, photograph and spot anything that could affect the design, budget or schedule. You then sit down with your designer in our showroom to compare cabinetry, counters, tile and fixtures at Good, Better and Best levels.

Once you approve the proposal and sign the design agreement, our in-house designers develop the plans: several layout options, a floor and demolition plan, a lighting and electrical plan, elevations, 3D renderings and a materials list with quantities. Design typically takes about 4–6 weeks. A few rounds of revisions are normal; deciding quickly is the easiest way to shorten this phase.

3D rendering of a navy and white kitchen design for a Melrose Park, PA remodel
A 3D rendering from the design phase of a Melrose Park kitchen.

Ordering and delivery (about 4–6 weeks)

Cabinetry usually sets the pace. Semi-custom and custom cabinets are built to order, and appliances, plumbing fixtures and specialty tile can have their own lead times. Once the design is approved, materials typically take about 4–6 weeks to be ordered and delivered. We track them and schedule the crew once they are ready, so your kitchen isn’t torn apart while everyone waits for a delivery.

Permits run in parallel. Requirements depend on your municipality and scope; in Philadelphia, plumbing and electrical work is permitted, and structural changes need more review. Our contracts ask for all selections at least two weeks before work starts.

Construction in your home (about 9–12 weeks)

A typical same-layout kitchen moves through these steps:

  1. Protection and demolition. Floors and nearby rooms are covered, dust walls go up, and the old kitchen comes out.
  2. Rough-in. Framing, plumbing, electrical and any ductwork, followed by rough inspections where required.
  3. Walls and floors. Insulation where needed, drywall, then flooring.
  4. Cabinets. Cabinets are installed, leveled and adjusted.
  5. Countertops. Stone and quartz counters are templated after cabinets are in, then fabricated and installed. Industry sources put that wait at roughly 1–2 weeks.
  6. Finishes. Backsplash, sink and faucet, appliances, lighting, hardware, trim and paint.
  7. Punch list and walkthrough. Every remaining item is finished, then we walk through the kitchen with you.

Kitchens with a new layout, structural changes or an addition usually take 12 weeks or more in this phase. A more detailed schedule is provided once the project scope is confirmed.

Finished kitchen with a warm wood island in Bala Cynwyd, PA, remodeled by dRemodeling
The same Bala Cynwyd kitchen, finished.

What makes a kitchen remodel take longer

  • Late or changed decisions. Changes after ordering can mean reordering and rescheduling. We document every change in writing first.
  • Backorders and special orders. Custom cabinetry, imported tile and panel-ready appliances can have long lead times.
  • Unforeseen issues. Opening walls and floors can reveal old wiring, rot or past work that isn’t to code.
  • Structural changes and permits. Engineering and plan review add time before work can start.
  • Inspections. Rough inspections have to pass before walls are closed.

Can you live at home during a kitchen remodel?

For most kitchen projects, yes. Set up a temporary kitchen in a dining room or basement with the refrigerator, a microwave, a coffee maker and a folding table, and plan simple meals. We protect the rest of the house with floor coverings and zipper walls, clean up daily and keep you updated weekly on progress and decisions needed.

Next step: Kitchen remodeling at dRemodeling · Full pricing guide · See our projects

Sources

  1. dRemodeling, Remodeling Costs & Pricing (planning ranges)
  2. dRemodeling, Our Process
  3. WTOP, “How long does a kitchen remodel take?” (March 2025)

Ranges and timelines are typical planning figures, not quotes. Your proposal reflects your home, scope and selections.

Planning a kitchen? Let’s map out your timeline.

Tell us about your project. We’ll reach out within one business day, or you can choose a convenient time for us to call you.

Scheduling a callback is optional.

SHOWROOM
7709 Ridge Avenue
Philadelphia, PA 19128
HOURS
Mon–Fri, 9 am – 5 pm
Showroom by appointment

Kitchen, bathroom and whole home remodeling in Philadelphia, the Main Line, Montgomery, Bucks, Delaware and Chester counties, and select areas of New Jersey.

Privacy policy